News Release: Crews complete work on Davy Crockett COFFERDAM

PORTLAND, Ore. - The barge Davy Crockett sits enclosed by a cofferdam in the Columbia River near Camas, Wash., April 18, 2011. The cofferdam will contain pollutants while work crews dismantle the barge and remove it from the river. Photo provided by Davy Crockett Response Unified Command.
Work crews completed installation of an 850-foot metal sheet-pile cofferdam around the barge Davy Crockett Monday.

The cofferdam includes an impermeable liner, which will trap any oil, tar balls and other pollutants in the enclosure while crews dismantle the vessel.

“Installation of the sheet pile barrier and an impermeable liner around the Davy Crockett is a significant step in controlling the environmental threats from this broken vessel,” said Coast Guard Capt. Daniel LeBlanc. “It will allow contractors to begin the process of carefully cutting the vessel into pieces, cleaning and removing the pieces from inside a protective cofferdam.”

The Davy Crockett Response Unified Command plans to begin the vessel’s destruction Thursday. Workers will separate the 229-foot stern section from the rest of the vessel first. This cut will take place underwater. After the cut, the stern will be refloated, which involves pumping off several hundred thousand gallons of ballast water.

Until then, crews will stage equipment and ensure the cofferdam is functioning according to plan.

INCIDENT BACKGROUND

The Washington Department Ecology received reports of oil sheen on the Columbia River near Vancouver, Wash., Jan. 27, 2011, and traced it 11 miles upstream to the 431-foot flat-deck barge Davy Crockett. Reports of sheen were reported as far as 15 miles downstream.

The vessel was partially sunk near the north shore between Vancouver and Camas, Wash., four miles upstream of the I-205 Bridge. The Davy Crockett had begun leaking oil due to improper and unpermitted salvage operations.

Response efforts began immediately to contain oil and stabilize the vessel. The Coast Guard, Washington Department of Ecology and Oregon Department of Environmental Quality are jointly managing the response and salvage effort using the National Incident Management System. 

In mid-February Coast Guard Commandant Adm. Robert Papp authorized Coast Guard Sector Columbia River to remove and destroy the barge Davy Crockett.  In his authorization memo, Adm. Papp stated that “destruction of this vessel is appropriate to mitigate the threat of continued discharge of oil, oil water mixtures and hazardous substances into the waterway.”  

OPERATIONS UPDATE, April 23, 2011

Work crews successfully separated the stern from the mid-section of the Davy Crockett Friday.

The on-site water filtration system that will treat the ballast water and oily water collected from tanks has been successfully tested. Equipment is being mobilized so the deballasting operation can begin later in the week. The treated water will be stored in a barge with large capacity tanks and ultimately disposed of at a local wastewater treatment plant.

SUMMARY INFORMATION

Date of Incident: Response began January 27, 2011
Location: North bank of the Columbia River near Camas, Washington
Product/Quantity: Lube, bunker and diesel oil; total quantity unknown.
Cause: Damaged derelict vessel.
Funding for response: Federal Oil Spill Liability Trust Fund

Source: Department of Ecology. State of Washington.  April 2011

Mare Island ship dismantler believes its bid on four vessels was best overall:

A Mare Island company's recent loss of some $2.5 million in a federal ship dismantling bid appears, on its face, to be a matter of only about $12,000.

But the loss could involve other factors not yet disclosed, officials said.

Allied Defense Recycling managing director Jay Anast said this week the small difference between bids from his company and the winning Texas ship dismantler is not bad for the company's first competitive bid.

"We lost it by 0.25 percent," Anast said. "That doesn't mean we're not competitive. It's very, very small dollars here that was the differential."

Anast questioned whether the U.S. Maritime Administration's decision to award the contracts to a company thousands of miles from the Suisun Bay Reserve Fleet's "mothball" vessels took into account the environmental impacts. He estimated the government would use about 1 million gallons of diesel fuel to haul the aging vessels to Texas.

Maritime Administration officials would not divulge what specific factors were considered in the award of the winning bid for the four vessels -- the Clamp, Sagamore, Reclaimer and Bolster. Agency spokeswoman Cheron Wicker would say only that bids are based on the "best value to the government."

Generally included in a best value assessment are price, capacity to actively and continuously work the vessel, past performance and completion schedule, Wicker wrote in an email.

Wicker added that unsuccessful bidders may request a debriefing with the Maritime Administration for further details.

Anast said he will seek a debriefing on how Allied Defense Recycling's bid compared to Marine Metals' winning bid. He alleged that the government did not add contingency funds to the price of the bid, in case of cost overruns. In particular, Anast said, repairs of aging ships while they are being cleaned to prepare for travel to Texas could easily bump a contract's value over the $12,000 bid difference between the two companies.

Anast went on to use the example of the M/V Lincoln. That ship was recently cleaned in preparation for the trip to Texas but a leak caused delay for unexpected repairs.

Were such ships to come straight to Mare Island, seaworthiness would not be an issue, Anast said. Allied Defense Recycling is dismantling two former mothball fleet vessels.

Maritime Administration officials were unable to immediately respond to Anast's concerns Thursday.

Contact staff writer Jessica A. York at (707) 553-6834 or jyork@timesheraldonline.com.

Source: Times-Herald. By Jessica A. York. 29 April 2011

Maersk closed shipbreaking recycling services, environmental concern in the shipping industry:

AP Moller Maersk Group ─ confirmed recently in Copenhagen, to stop the ship to the other owner to provide intermediary services, environmental scrap recycling, claiming to be more focus on core business in shipping. The decision is not only the outside world I am truly an accident, caused by the shipping industry while promoting environmental protection concerns shipbreaking.

Maersk ships in China and the Netherlands scrap recycling services, both for the Group's own ship scrapping arrangements to provide environmental protection, while providing similar shares for other business owners, customers Ro-ro shipping companies such as Sweden and the Netherlands Shell Hualin. The old boat will be arranged involving China's shipbreaking into Terminal, the group's shipbreaking services to the department responsible for planning and supervision of shipbreaking process to ensure environmental protection and the dismantling process in line with the requirements of low pollution, and recycling of scrap metal.

Indian shipbreaking site in the peninsula's many" red beach" form of shipbreaking, although the owner earnings will be higher, However, the safety hazards to workers and the environment. Maersk has stated that no" red beach", also set up shiprecycling service department, the Office of Rotterdam in the Netherlands with 84 employees and offices in China, there were four employees, has been handling about 60 old vessels, most of which Maersk does not own boats.

The group said that no arrangements for other environmentally friendly shipbreaking shipowners, shipping in order to focus more on core business of the future and further Enhance the competitiveness in the industry. But the statement also stressed that this decision will not affect the group as a whole scrap recycling policy, its own old ships will continue to deal with security and sustainable development concept.

However, the industry was surprised by the decision, because the business is not able to profit, they can improve the environmental considerations Group's image. Moreover, some insiders think that in 2009 in Hong Kong is an international Ship Recycling Convention, adopted the" Hong Kong Convention," the frustration, because the Maersk ship scrap recycling services in the implementation of some provisions of the Department, such as the development list of hazardous substances and recycling programs.

Source: en.zgxu.com. 26 April 2011

Mare Island dismantler gets no traction on new contract bids:

Four Mothball Fleet ship-dismantling contracts posted Monday shut out a Mare Is-land ship industry newcomer.

Marine Metals of Brownsville, Texas, will scrap and recycle the Suisun Bay Reserve Fleet ships Clamp, Sagamore, Reclaimer and Bolster for $1.85 million, according to the U.S. Maritime Administration's contracts posted online Monday. The four vessels will be cleaned in two batches at the BAE Systems San Francisco Ship Repair starting in mid-May, and then will be towed through the Panama Canal to Texas.

The separate hull-cleaning contracts range from about $144,000 to $153,000 each.

Allied Defense Recycling on Mare Island since late last year had bid on the contracts, its first competitive bid for the company since the Maritime Administration this year awarded the startup company no-bid contracts worth $3.1 million to dismantle the SS President and SS Solon Turman.

Company managing director Jay Anast declined Monday to comment on the contract awards, saying he needed to review them.

In other ship-recycling news, a vessel contracted out to All Star Metals, also in Texas, apparently began to leak after it was cleaned in San Francisco last week, a Maritime Administration spokeswoman wrote in an email. The M/V Lincoln was pumped out and repaired, she said, and is still scheduled for a final trip to Texas.

Source: (Vallejo) Times-Herald. By Jessica A. York. 25 April 2011
http://www.mercurynews.com/breaking-news/ci_17926277?nclick_check=1

Green Ship Recycling: Wilhelmsen Ship Management

Green ship recycling is the new and additional Green product in WSM's portfolio.

Green Ship Recycling services is specially designed for the socially responsible Green ship owners whom demands a demolition process that offers safe working environment at the yard, together with safe removal and disposal of hazardous materials on board.
With green awareness in mind, we have signed agreements with key yards in China to carry out ship recycling work, in compliance with IMO requirements although they are not yet ratified.  The recycling work will be monitored by our site team members who have the authority to "stop work" in case of any deviation from established green procedures.  The yards have agreed to be monitored against a set of Key Performance Indexes (KPIs) which will decide a previously agreed bonus incentive scheme for them.  This comprehensive agreement with the selected yards are unique and the one of its kind in the industry.  We hope to expand the portfolio by getting more and more shipyards to go 'Green'.

The process of green recycling is tedious and requires proper planning and preparation.  One acceptable approach is "Demolition" which is the actual cutting up of the ship in blocks of manageable sizes.  The correct trimming, steel cutting including the removal arrangements are critical.  The blocks with oil content and machinery are placed in special areas on shore with proper drainage and containment arrangements.  Fire fighting procedures and evacuation routes are manned properly.

"Pre-cleaning" is a requirement prior demolition.  Pre-cleaning is the safe removal of all hazardous materials and wastes such as asbestos, fuel oils and lubes, cable insulation and other PCBs, deck coverings and insulation materials, gases and refrigerants (CFC), paints and thinners, stores and spares, fire alarm sensors and radio active materials and all other hazardous and potentially hazardous materials.  An IHM / Green Passport is pre-requisite prior to recycling.

The process of Demolition and Pre-Cleaning are fully documented in a 'Green Recycle Plan' - a document developed using the IHM / Green Passport with inputs from yard and WSM.  This plan is vital towards green recycling.
WSM also provides IHM (Inventory of Hazardous Materials) / Green Passport services for existing and to be recycled vessels by our in-house experts who are trained and certified by Class.  IHM / Green Passport which is WSM's other green product was rolled out in April 2010.

WSM's objective is to implement a proper health, safety and environmental approach towards ship recycling.  We hope to work with more shipowners in this project to ensure a better and healthier living on earth.

Source: Wilhelmsen Ship Management
http://www.wilhelmsen.com/services/maritime/companies/barbership/Pages/greenshiprecycling.aspx